Engineering record time: July 19, 2021
Main structural engineering: 100% completed
Aluminum door and window exterior decoration project: 90% completed, 3-29 floor window frame installation, aluminum clad plate, grille, glass railing embedded parts installation, aluminum door and window exterior decoration.The project is expected to be completed by the end of July 2021
Secondary decoration project: 98% completed, wall plastering is expected to be completed by the end of January 2021, interior and exterior wall paint is expected to be completed by the end of July 2021
Ceiling project: 90% completed, expected to be completed in early August 2021
The tiling project: 90% has been completed and is expected to be completed in early August 2021
Electrical and mechanical wiring engineering: 95% has been completed and is expected to be completed by the end of July 2021
Air-conditioning project: 90% completed, air-conditioning piping is expected to be completed by the end of May 2021, air-conditioning installation is expected to be completed on July 30, 2021
Fine decoration: 65% has been completed, it is expected to be August 30, 2021
Engineering record time: April 09, 2021
Main structural engineering: completed
Aluminum doors and windows exterior decoration project: 68% has been completed, 3-29 floor window frame installation, aluminum cladding, grille, glass railing embedded parts installation, aluminum doors and windows exterior decoration project is expected to be completed by the end of May 2021.
The second decoration project: 80% has been completed, the wall plastering is expected to be completed by the end of January 2021, and the interior and exterior wall paint is expected to be completed by the end of May 2021.
Ceiling project: 60% has been completed and is expected to be completed by the end of February 2021.
The tiling project: 45% has been completed and is expected to be completed by the end of May 2021.
Electrical and mechanical wiring engineering: 92% has been completed and is expected to be completed by the end of May 2021.
Air-conditioning project: 55% has been completed, the air-conditioning piping is expected to be completed by the end of February 2021, and the air-conditioning installation is expected to be completed on June 30, 2021.
Fine decoration: 38% has been completed, and it is expected to be on July 31, 2021.
工程記錄時間:2019年6月10日
工程項目:結構體工程
已進行工期天數:637
工程施工尚餘天數:308天
實際進度:65%
說明:6月份完成3FL樓地板灌漿,混凝土養護放樣,外牆鷹架施工
工程記錄時間:2019年2月28日
工程項目:結構體工程
已進行工期天數:536
工程施工尚餘天數:115天
實際進度:63.7%
說明:1月份完成B2樓地板、B1支撐架設。
2019年2月工程縮時攝像
↓↓↓
http://v.qq.com/x/page/l0844svvybj.html
工程記錄時間:2019年1月31日
工程項目:結構體工程
已進行工期天數:506
工程施工尚餘天數:145天
實際進度:62.2%
說明:1月份完成B3樓地板、進行環形支撐第二層拆除清運。
2019年1月工程縮時攝像
↓↓↓
http://v.qq.com/x/page/n0844nsrapo.html
工程記錄時間:2018年12月31日
工程項目:結構體工程
已進行工期天數:474
工程施工尚餘天數:177天
實際進度:60%
說明:12月份完成地梁澆注完成、環形支撐第三層拆除清運、電梯井組模。
工程記錄時間:2018年11月30日
工程項目:結構體工程
已進行工期天數:445
工程施工尚餘天數:206天
實際進度:55.3%
說明:11月份完成連續壁大底板澆注完成,地梁模板安裝完成約99%,地梁頂部主筋鋼筋綁紮施工。
工程記錄時間:2018年10月31日
工程項目:結構體工程
已進行工期天數:413
工程施工尚餘天數:238天
實際進度:54.1%
說明:10月份完成第四層土方開挖及清運,單項工程有預留柱打鑿完成90%,承台澆築完成量60%。
工程記錄時間:2018年9月30日
工程項目:結構體工程
已進行工期天數:384
工程施工尚餘天數:267天
實際進度:50.4%
說明:9月份完成單項工程有第三道環形支撐,正進行第四層土方開挖,總方量4600立方米,開挖完成量2760立方米,第四層開挖60%。
工程記錄時間:2018年8月30日
工程項目:結構體工程
已進行工期天數:325
工程施工尚餘天數:326天
實際進度:49.3%
說明:8月份完成單項工程有第二道環形支撐,正進行第三層土方開挖,開挖完成量2256立方米,第三層開挖48%。